Once a control states when to act and what to do, evaluation answers the question that naturally follows, which is whether it worked. Evaluation lives at the control layer because the control already supplies both halves of the measurement problem. Its versions define the unit of comparison, recording which algorithm ran and when it changed, while its criteria define the moment of measurement, since the same condition that fires the action is the condition whose cost you want to know.

Versioned controls

Each version of a control is a criteria and action pair. Exactly one version is active at a time, and the platform records whenever the active version switches:
Versioning is what makes a control evaluable in the first place. Answering “did the change work?” requires a before and an after, or two algorithms to compare, and the version history provides both without anyone having to reconstruct what was running at a given time.

Version comparison

When the active version switches, the pre/post comparison derives automatically from the control itself, comparing the measures its criteria read, along with the KPIs downstream of them in the Metric Tree, across the switch date. Two versions can also run side by side, with some entities assigned to each, which controls for seasonality and external shocks in a way that a simple pre/post comparison cannot. In either case the comparison metric comes from the control definition rather than from an analysis someone assembles by hand, so every control accumulates a track record of what its changes did.

Mechanistic impact measurement

Whereas version comparison observes how KPIs move, the longer-term method prices the events themselves. The insight is that the criteria already mark the moment that matters: if a control’s criteria fire on a stockout, then measurement should fire on that stockout too. The control simply declares what each firing costs:
Each firing is then priced as the revenue lost at the SKU-store grain over the window during which the condition held. A version’s impact becomes the sum of its priced events, so comparing versions turns into comparing priced events rather than hoping that a KPI shift can be attributed to the change. The counterfactual measure and its window resolve in the semantic engine, which is where this mechanism will be built.

Backtesting

A version does not need to run in production before it can be evaluated. Executing its criteria against history produces a trace of every day it would have fired, shown side by side with what the active version actually did, and the same evaluation block prices that trace. You can therefore backtest a proposed version before adopting it and measure it afterward, with both answers coming from the same definitions.

Learning drivers

Evaluation is also how the World Model learns causal magnitudes. The metric tree’s driver edges are qualitative by design, stating what drives what but deliberately not how much, because a magnitude can only be identified through intervention and a control is the thing that intervenes. When a control acts on a driver, its measured results (version comparisons, side-by-side runs, and priced firings) estimate how much that driver moves the KPI. The estimate keeps updating as the control continues to act, carries a confidence that grows with the number of interventions, and supersedes any observational fit. In other words, while the physics knows what drives what, a control learns how much by acting. A KPI whose drivers carry no control-learned magnitudes is being navigated on correlation alone, and the World Model graph makes this visible by showing, for each edge, whether its magnitude comes from interventions or from observation.

Feeding the physics

Evaluation results flow back into calibration. When a change’s measured impact disagrees with what the model implied, the gap points at a specific physical claim, such as a lead time or a demand response, and the physics layer updates accordingly, so that the model the next decision runs on is sharper than the one before it.

Next steps

Controls

The criteria and action pairs that versions carry

Calibration

Where evaluation results update the physics

Metric Tree

The KPIs downstream of a control’s criteria

Opportunity sizing

Find where a better control is worth the most